Rendering - MS Science Lab2003 Bond Status Report Banner
     $ Difference
Project Summary    Plan    Actual      + Over / - Under
Wood Middle School Science Labs
Start Date Mar 2004 Feb 2004  - 1
Completion Date
Aug 2005 Aug 2005   0
Total Project Cost $ 4,896,122 $ 4,801,954  - $ 94,168
Building Only Cost (Constr. Contracts)   $ 3,945,234  
Site & Design Development (17.5 acres)
  $ 522,881  
Cost per Sq. Ft.   $ 28.97  
Facility Gross Total Sq. Footage
  136,207 sq. ft.  
Technology   $ 159,978  
Facility Furniture, Fixtures & Equip.   $ 16,136  
ROCIP   $ 49,516  
Construction Management Services   $ 108,209  
Progress Bar - Current Phase of Construction
Progress Bar - Substantial Completion
Project Team
Logo - O'Neil, Conrad & Oppelt Architect: O'Neill, Conrad, Oppelt - Architects
Logo - Garza Bomberger & Associates Architect: Garza Bomberger & Associates
Logo - Bartlett-Cocke GC General Contractor (GC): Bartlett-Cocke General Contractors
Tommy Bonecutter Project Coordinator, NEISD, Construction Management
Larry Goslin MEP Inspector, NEISD, Construction Management
Plan Details Bid Award Presentation - June 2005
Progress Photos Wood MS - Progress Photos
Wood MS Campus: 14800 Judson Road, San Antonio, TX 78233
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues