White MS Clinic - Smry -- NEISD.net

Construction Management & Engineering

CM&E Home | Our Mission | 2003 Bond Program Status | Engineering | Warranty | ConstructWare
 
<Previous Page 1 of 2 Next>
Rendering - MS Science Lab - 1 Story2003 Bond Status Report Banner
     $ Difference
Project Summary    Plan    Actual      + Over / - Under
White Middle School - Science Labs and Nurse's Clinic
Start Date May 2005 Nov 2005  6 months
Completion Date
Nov 2006 Oct 2006  - 1 month   
Total Project Cost $ 4,731,887 $ 5,041,380 $ 309,493
Building Only Cost (Constr. Contracts)   $ 4,367,082  
Site & Design Development
  $ 321,785  
Building Only - Cost per Sq. Ft.   $ 260.72  
Facility Gross Total Sq. Footage
  16,750 sq. ft.  
Technology   $ 161,535  
Facility Furniture, Fixtures & Equip.   $ 16,248  
ROCIP   $ 54,752  
Construction Management Services   $ 119,978  
Progress Bar - Current Phase of Construction
Progress Bar - Under Construction
Project Team
Logo - Garza Bomberger & Associates Architect: Garza Bomberger & Associates
Logo - O'Neil, Conrad & Oppelt Architect: O'Neill, Conrad, Oppelt - Architects
Logo - Bartlett-Cocke GC General Contractor (GC): Bartlett-Cocke General Contractors
Tommy Bonecutter Project Coordinator, NEISD, Construction Management
Larry Goslin MEP Inspector, NEISD, Construction Management
Plan Details Bid Award Presentation - June 2005
White MS Campus: 7800 Midcrown, San Antonio, TX 78218
 
<Previous Page 1 of 2 Next>
This page was last updated on July 07, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues