Walzem ES - Smry -- NEISD.net

Construction Management & Engineering

CM&E Home | Our Mission | 2003 Bond Program Status | Engineering | Warranty | ConstructWare
 
<Previous Page 1 of 2 Next>
Photo - Walzem ES2003 Bond Status Report Banner
         $ Difference
Project Summary    Plan    Actual    + Over / - Under
Walzem Elementary School
Start Date Apr 2005 Jul 2005 + 3
Completion Date
Sept 2006 Jul 2006  - 2
Total Project Cost $ 5,420,000 $ 6,388,838 +  $ 968,838
Building Only Cost (Constr. Contracts)   $ 5,358,000  
Site & Design Development
  $ 559,061  
Building Only Cost per Sq. Ft.   $ 98.17  
Facility Gross Total Sq. Footage
  54,580 sf.  
Technology   $ 187,197  
Facility Furniture, Fixtures & Equip   $ 70,374  
ROCIP   $ 67,248  
Construction Management Services   $ 146,958  
Progress Bar - Current Phase of Construction
Progress Bar - Substantial Completion
Project Team
Logo - DeMunbrun-Scarnato Assoc. Architect: Demunbrun-Scarnato Associates
Logo - Bartlett-Cocke GC General Contractor (GC): Bartlett Cocke General Contractors
Woody Johnson Project Coordinator, NEISD, Construction Management
Jeffrey Hoffman MEP Inspector, NEISD, Construction Management
Progress Photos Walzem ES - Progress Photos
Walzem ES Campus: 4618 Walzem, San Antonio, TX 78218
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering