Project Details
Roosevelt High School
This Facility includes:  
Replace Original Academic Facility with New Structures
     60 Classrooms with Workroom & Storage Areas
     52 Areas for Supporting Programs
               (Fine Arts, ROTC, Health, Greco Building, etc.)
     Library
     Kitchen / Cafeteria Dining Area / Auditorium (1,000 seats)
     Athletic Facilities
               (2 Gyms, PE Offices & Storage, etc.)
     Administrative Area with Nurse Station
Phased Project Over 4 Years
     Roosevelt HS Replacement Project
               Package III / IIIA - JROTC / CP
                             Construction Start @ Oct 2004
                             Construction Completion @ Sep 2005
               Package IV - Greco Building Finish-Out Package
                              Construction Start @ Jun 2005
                              Construction Completion @ Dec 2006 - 2007 - 2008 (Various)
                              Package IVA - Site Package
                              Package IVB - Foundation / Structure
                              Package IVC - Greco Building Construction
                                  Exterior Masonry Wall
                                  Roof & Interior Finish-Out
               Package V - Administration / Library / CT
                              Construction Start @ Apr 2007
                              Construction Completion @ Jun 2009
               Package VI - Auto Shop
                              Construction Start @ Jul 2005
                              Construction Completion @ Feb 2006
               Asbestos & Portable Move & Support Cost
                              Construction Start @ Jun 2005
                              Construction Completion @ Dec 2006 - Dec 2007
Maintain DATA & Arts & Science Facilities
 
Site Work & Hardscape Improvements
 
Construct additional Parking
     Expand Campus Parking Capacity
Roosevelt HS - Site Plans:
Roosevelt HS - Site Plan
 
Roosevelt HS - Site Plan
 
Roosevelt HS - Greco - Floor Plan 1
 
Roosevelt HS - Greco - Floor Plan 2
 
 
<Previous Page 2 of 2 CM&E Home >
This page was last updated on July 06, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues.