         $ Difference
Project Summary    Plan    Actual     + Over / - Under
Ridgeview Elementary School
Start Date Jun 2005 Apr 2005  - 2
Completion Date
Dec 2006 Aug 2006   - 4 
Total Project Cost $ 4,340,000 $ 5,028,199 +  $ 688,199
Building Only Cost (Constr. Contracts)   $ 4,123,551  
Site & Design Development   $ 534,162  
Building Only Cost per Sq. Ft.   $ 98.53  
Facility Gross Total Sq. Footage   41,850 sf.  
Technology   $ 151,857  
Facility Furniture, Fixtures & Equip.   $ 53,775  
ROCIP   $ 51,755  
Construction Management Services   $ 113,100  
Progress Bar - Current Phase of Construction
Progress Bar - Substantial Completion
Project Team
  Architect: Lopez-Salas Architects
  General Contractor (GC): Baron Long Construction Co.
Abie Flores Project Coordinator, NEISD, Construction Management
Shane Crawford MEP Inspector, NEISD, Construction Management
Progress Photos Ridgeview ES - Progress Photos
Ridgeview ES Campus: 8223 North McCullough, San Antonio, TX 78216
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues.