Nimitz Middle School - Locker Improvements - Details
         $ Difference
Project Summary    Plan Actual  + Over / - Under
Start Date May 2005      Sept 2005     4 months   
Completion Date
Various  Jan 2006   - 0 -   
Lockers Only Cost (Constr. Contracts) $ 169,152 $ 144,378 - $ 24,774
This Locker Improvement Project includes:
Upgrade Existing MS Lockers to a Uniform District Standard
Locker systems at each campus will be replaced and/or repaired in a phased approach to facilitate continued operation at each campus
     Replacement of academic lockers
     Replacement of physical education lockers
     Replacement of athletic lockers
     Finish-out of all transitions between new locker systems and
     existing wall, soffit and floor conditions
Nimitz MS - Lockers - Site Plan:
 
Rendering-Lockers
 
<MS Lockers Page 2 of 2 CM&E Home >
This page was last updated on July 31, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering