New Schools - Summary -- NEISD.net

Construction Management & Engineering
CM&E Home | Our Mission | 2003 Bond Program Status | Engineering | Warranty | ConstructWare
 
<Previous Page 1 of 2 Next >
Rendering - MS Science Lab - 1 Story Elevation2003 Bond Status Report Banner
     $ Difference
Project Summary    Plan   
Actual
  + Over / - Under
New Schools
Start Date 2005-2007 2006-2008  Various
Completion Date
2006-2008 2006-2008  Various
Total Project Cost $ 212,270,000 $ 235,355,012 $ 23,085,012
Building Only Cost (Constr. Contracts)   $ 195,568,706  
Site & Design Development (9 campuses)
  $ 13,158,499  
Technology   $ 7,011,068  
Facility Furniture, Fixtures & Equip.   $ 11,838,782  
ROCIP   $ 2,405,038  
Construction Management Services   $ 5,372,920  
Progress Bar - Current Phase of Construction
Progress Bar - Under Construction Phase
New School Links  
Bulverde Creek ES: Bulverde Creek ES - Project Summary Bulverde Creek ES - Project Details
Canyon Ridge ES: Canyon Ridge ES - Project Summary Canyon Ridge ES - Project Details
Steubing Ranch ES: Steubing Ranch ES - Project Summary Steubing Ranch ES - Project Details
Wilderness Oak ES: Wilderness Oak ES - Project Summary Wilderness Oak ES - Project Details
Jose M. Lopez MS: Lopez MS - Project Summary Lopez MS - Project Details
Dr. Bernard Harris MS: Harris MS - Project Summary Harris MS - Project Details
Claudia Taylor Lady Bird Johnson HS: CT Johnson HS - Project Summary CT Johnson HS - Project Details
 
<Previous Page 1 of 2 Next >
This page was last updated on June 19, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues