     $ Difference
Project Summary    Plan    Actual      + Over / - Under
Madison High School
Start Date Jul 2005 Jul 2005  0
Completion Date
May 2007 Aug 2007  3 month   
Total Project Cost $ 18,160,000 $ 17,578,488 - $ 581,512
Building Only Cost (Constr. Contracts)   $ 15,233,466  
Site & Design Development
  $ 1,226,062  
Building Only - Cost per Sq. Ft.   $ 260.72  
Facility Gross Total Sq. Footage
  16,750 sq. ft.  
Technology   $ 330,000  
Facility Furniture, Fixtures & Equip.   $ 179,458  
ROCIP   $ 190,988  
Construction Management Services   $ 418,514  
Progress Bar - Current Phase of Construction
Progress Bar - Under Construction
Project Team
Logo - Pfluger, Architects Architect: Pfluger - Architects
Logo - Bartlett-Cocke General Contractor (GC): Bartlett-Cocke General Contractors
Abie Flores Project Coordinator, NEISD, Construction Management
Shane Crawford MEP Inspector, NEISD, Construction Management
Plan Details Bid Award Presentation - August 2005
Madison H S Campus: 5005 Stahl Road , San Antonio, TX 78247
 
<Previous Page 1 of 2 Next>
This page was last updated on June 26, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues