| Project Summary |
Plan |
Actual |
+ Over / - Under |
| Middle School Lockers - 8 Campuses |
| Start Date |
May 2005 |
Sept 2005 |
4 months |
Completion Date
|
Various |
Jan 2006 |
- 0 - |
| Total Project Cost |
$ 1,500,000 |
$ 1,493,134 |
- $ 6,866 |
| Lockers Only Cost (Constr. Contracts) |
|
$ 1,402,678 |
|
Site & Design Development
|
|
$ 51,920 |
|
| Lockers Only - Avg. Cost per Campus (8) |
|
$ 165,632 |
|
| Construction Management Services |
|
$ 38,536 |
|
| Progress Bar - Current Phase of Construction |
 |
| Project Team |
 |
Prime Consultant: Jorge Cabello, PE
Director-Construction Planning & Design,
NEISD, Construction Management
Project Coordinator: Tommy Bonecutter
NEISD, Construction Management
MEP Inspector: Larry Goslin
NEISD, Construction Management |
 |
General Contractor (GC): DeBourgh Manufacturing |
| Plan Details |
Bid Award Presentation - April 2005 |
| Lockers - Middle School Campuses - Details |
| Bradley MS: |
14819 HeimerRoad, San Antonio, TX 78232 |
| Eisenhower MS: |
8231 Blanco Road, San Antonio, TX 78216 |
| Garner MS: |
4302 Harry Wurzbach Road, San Antonio, TX 78209 |
| Jackson MS: |
4538 Vance Jackson Road, San Antonio, TX 78230 |
| Krueger MS: |
438 Lanark Road, San Antonio, TX 78218 |
| Nimitz MS: |
5426 Blanco Road, San Antonio, TX 78218 |
| White MS: |
7800 Midcrown Road, San Antonio, TX 78218 |
| Wood MS: |
14800 Judson Road, San Antonio, TX 78233 |
| |
| <Previous |
Page 1 of 2 |
Next> |
This page was last updated on July 31, 2006.
Please contact Theresa Gray,
Web Master,
Construction Management and Engineering
at 804-7270, ext. 372,
regarding webpage-related issues |
| |
| |
|
| |
| | | |
|
|