lockers-ms-smry -- NEISD.net

Construction Management & Engineering

CM&E Home | Our Mission | 2003 Bond Program Status | Engineering | Warranty | ConstructWare
 
<Previous Page 1 of 2 Next>
Photo-Lockers2003 Bond Status Report Banner
     $ Difference
Project Summary    Plan    Actual      + Over / - Under
Middle School Lockers - 8 Campuses
Start Date May 2005         Sept 2005        4 months   
Completion Date
Various          Jan 2006     - 0 -   
Total Project Cost $ 1,500,000 $ 1,493,134 - $ 6,866
Lockers Only Cost (Constr. Contracts)   $ 1,402,678  
Site & Design Development
  $ 51,920  
Lockers Only - Avg. Cost per Campus (8)   $ 165,632  
Construction Management Services   $ 38,536  
Progress Bar - Current Phase of Construction
Progress Bar - Substantial Completion
Project Team
Logo - North East ISD Prime Consultant: Jorge Cabello, PE
                           Director-Construction Planning & Design,
                           NEISD, Construction Management

Project Coordinator: Tommy Bonecutter
                           NEISD, Construction Management

MEP Inspector: Larry Goslin
                           NEISD, Construction Management
Logo - DeBourgh Manufacturing

General Contractor (GC):
DeBourgh Manufacturing
Plan Details Bid Award Presentation - April 2005
Lockers - Middle School Campuses - Details
Bradley MS: 14819 HeimerRoad, San Antonio, TX 78232
Eisenhower MS: 8231 Blanco Road, San Antonio, TX 78216
Garner MS: 4302 Harry Wurzbach Road, San Antonio, TX 78209
Jackson MS: 4538 Vance Jackson Road, San Antonio, TX 78230
Krueger MS: 438 Lanark Road, San Antonio, TX 78218
Nimitz MS: 5426 Blanco Road, San Antonio, TX 78218
White MS: 7800 Midcrown Road, San Antonio, TX 78218
Wood MS: 14800 Judson Road, San Antonio, TX 78233
 
<Previous Page 1 of 2 Next>
This page was last updated on July 31, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues