Harris MS - Summary -- NEISD.net

Construction Management & Engineering

CM&E Home | Our Mission | 2003 Bond Program Status | Engineering | Warranty | ConstructWare
 
<Previous Page 1 of 2 Next>
Rendering - Harris MS2003 Bond Banner
         $ Difference
Project Summary    Plan    Actual    + Over / - Under
Dr. Bernard A. Harris, Jr. Middle School
Start Date Jan 2005 Feb 2005 + 1
Completion Date
Jul 2006 Jun 2006 - 1
Total Project Cost $ 31,869,386 $ 33,924,926  $ 2,055,540
Building Only Cost (Constr. Contracts)   $ 27,254,034  
Site & Design Development (40.0 acres)   $ 2,309,755  
Cost per Sq. Ft.   $ 132.95  
Facility Gross Total Sq. Footage
  205,000 sf.  
Technology   $ 1,007,387  
Facility Furniture, Fixtures & Equip.   $ 2,264,168  
ROCIP   $ 342,064  
Construction Management Services   $ 747,517  
Progress Bar - Current Phase of Construction
Progress Bar - Substantial Completion
Project Team
Logo - Pfluger Associates Project Architect: Pfluger Associates
Logo - Chumney & Assoc. Architect: Chumney & Associates
Logo - Joeris General Contractors General Contractor (GC): Joeris General Contractors
Tom Edwards Project Coordinator, NEISD, Construction Management
Bernard Ciulla MEP Inspector, NEISD, Construction Management
Progress Photos - A Harris MS - Progress Photos - Set A
Progress Photos - B Harris MS - Progress Photos - Set B
Progress Photos - C Harris MS - Progress Photos - Set C
Progress Photos - D Harris MS - Progress Photos - Set D
Harris MS Campus: 5300 Knoll Creek, San Antonio, TX
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues.