Eisenhower MS Science - Smry -- NEISD.net

Construction Management & Engineering

CM&E Home | Our Mission | 2003 Bond Program Status | Engineering | Warranty | ConstructWare
 
<Previous Page 1 of 2 Next>
Rendering - MS Science Lab2003 Bond Status Report Banner
     $ Difference
Project Summary    Plan    Actual      + Over / - Under
Eisenhower Middle School - Science Labs
Start Date Jan 2006 Nov 2005  - 2
Completion Date
Jul 2007 Jan 2007  - 6
Total Project Cost $ 5,556,848 $ 6,139,907 $ 583,059
Building Only Cost (Constr. Contracts)   $ 5,164,757  
Site & Design Development
  $ 579,365  
Building Only Cost per Sq. Ft.   $ 235.83  
Facility Gross Total Sq. Footage
  21,900 sq. ft.  
Technology   $ 158,796  
Facility Furniture, Fixtures & Equip.   $ 30,509  
ROCIP   $ 64,823  
Construction Management Services   $ 141,658  
Progress Bar - Current Phase of Construction
Progress Bar - Under Construction
Project Team
Logo - Garza Bomberger & Associates Architect: Garza Bomberger & Associates
Logo - O'Neil, Conrad & Oppelt Architect: O'Neill, Conrad, Oppelt - Architects
Logo - Bartlett-Cocke GC General Contractor (GC): Bartlett-Cocke General Contractors
Tommy Bonecutter Project Coordinator, NEISD, Construction Management
Larry Goslin MEP Inspector, NEISD, Construction Management
Plan Details Bid Award Presentation - June 2005
Progress Photos Eisenhower MS - Progress Photos
Eisenhower MS Campus: 8231 Blanco Road, San Antonio, TX 78216
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.