     $ Difference
Project Summary    Plan    Actual      + Over / - Under
Driscoll Middle School - Nurse's Clinic
Start Date Aug 2006 Apr 2006  - 4 months
Completion Date
Apr 2008 Sep 2006  - 19 months
Total Project Cost $ 292,791 $ 268,598 - $ 24,193
Building Only Cost (Constr. Contracts)   $ 220,986  
Site & Design Development
  $ 30,612  
Cost per Sq. Ft.   $  
Facility Gross Total Sq. Footage
  sq. ft.  
Technology   $ 3,854  
Facility Furniture, Fixtures & Equip.   $ 4,311  
ROCIP   $ 2,774  
Construction Management Services   $ 6,061  
Progress Bar - Current Phase of Construction
Progress Bar - Substantial Completion
Project Team
Logo - Garza Bomberger & Associates Architect: Garza Bomberger & Associates
Logo - O'Neil, Conrad & Oppelt Architect: O'Neill, Conrad, Oppelt - Architects
Logo - Bartlett-Cocke GC General Contractor (GC): Bartlett-Cocke General Contractors
Tommy Bonecutter Project Coordinator, NEISD, Construction Management
Larry Goslin MEP Inspector, NEISD, Construction Management
Plan Details Bid Award Presentation - June 2005
Progress Photos Driscoll MS - Progress Photos
Driscoll MS Campus: 17150 Jones-Maltsberger, San Antonio, TX 78247
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues