Colonial Hills ES - Smry -- NEISD.net

Construction Management & Engineering

CM&E Home | Our Mission | 2003 Bond Program Status | Engineering | Warranty | ConstructWare
 
<Previous Page 1 of 2 Next>
Photo - Walzem ES2003 Bond Banner
         $ Difference
Project Summary    Plan    Actual     + Over / - Under
Colonial Hills Elementary School
Start Date May 2005 Apr 2005  - 1
Completion Date
Oct 2006 Aug 2006  - 2
Total Project Cost $ 5,140,000 $ 5,788,339 +  $ 648,339
Building Only Cost (Constr. Contracts)   $ 4,689,000  
Site & Design Development   $ 642,138  
Building Only Cost per Sq. Ft.   $ 92.03  
Facility Gross Total Sq. Footage
  50,950 sf.  
Technology   $ 182,157  
Facility Furniture, Fixtures & Equip.   $ 87,584  
ROCIP   $ 58,851  
Construction Management Services   $ 128,609  
Progress Bar - Current Phase of Construction
Progress Bar - Substantial Completion
Project Team
Logo - McChesney Architects Architect: McChesney Architects
Logo - Greco Construction General Contractor (GC): Greco Construction Co.
Abie Flores Project Coordinator, NEISD, Construction Management
Shane Crawford MEP Inspector, NEISD, Construction Management
Progress Photos Colonial Hills ES - Progress Photos
Colonial Hills ES Campus: 2627 Kerrybrook, San Antonio, TX 78230
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.