Churchill High School
Start Date Jul 2005 Jul 2005  0
Completion Date
May 2007 Aug 2007  3 month   
Total Project Cost $ 24,160,000 $ 24,532,757 $ 372,757
Building Only Cost (Constr. Contracts)   $ 20,966,243  
Site & Design Development
  $ 1,873,040  
Building Only - Cost per Sq. Ft.   $ 260.72  
Facility Gross Total Sq. Footage
  16,750 sq. ft.  
Technology   $ 630,270  
Facility Furniture, Fixtures & Equip.   $ 225,000  
ROCIP   $ 263,146  
Construction Management Services   $ 575,057  
Progress Bar - Current Phase of Construction
Progress Bar - Under Construction
Project Team
Logo - Garza Bomberger & Assoc. Architect: Garza Bomberger & Associates
Logo - Joeris General Contractors General Contractor (GC): Joeris General Contractors
Tom Edwards Project Coordinator, NEISD, Construction Management
Bernard Ciulla MEP Inspector, NEISD, Construction Management
Plan Details Bid Award Presentation - August 2005
Progress Photos Churchill HS - Progress Photos
Churchill HS Campus: 12049 Blanco Road , San Antonio, TX 78216
 
<Previous Page 1 of 2 Next>
This page was last updated on July 05, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues