| Building Only Cost (Constr. Contracts) |
|
$ 13,328,257 |
|
Site & Design Development (19.2 acres)
|
|
$ 458,460 |
|
Facility Gross Total Sq. Footage
|
|
108,285 sf. |
|
| Facility Furniture, Fixtures & Equip. |
|
$ 930,162 |
|
| Construction Management Services |
|
$ 365,564 |
|
| Progress Bar - Current Phase of Construction |
 |
Architect: Chumney & Associates |
 |
General Contractor (GC):Spaw Glass General Contractors |
| Abie Flores |
Project Coordinator, NEISD, Construction Management |
| Shane Crawford |
MEP Inspector, NEISD, Construction Management |