Bulverde Creek ES - Summary -- NEISD.net

Construction Management & Engineering

CM&E Home | Our Mission | 2003 Bond Program Status | Engineering | Warranty | ConstructWare
 
<Previous Page 1 of 2 Next>
Photo - Bulverde Creek ES2003 Bond Banner
         $ Difference
Project Summary    Plan    Actual    + Over / - Under
Bulverde Creek Elementary School
Start Date Mar 2004 Mar 2004   0
Completion Date
Aug 2005 Aug 2005   0
Total Project Cost $ 16,612,049 $ 15,752,629  - $ 859,420
Building Only Cost (Constr. Contracts)   $ 13,328,257  
Site & Design Development (19.2 acres)
  $ 458,460  
Cost per Sq. Ft.   $123.09  
Facility Gross Total Sq. Footage
  108,285 sf.  
Technology   $ 502,903  
Facility Furniture, Fixtures & Equip.   $ 930,162  
ROCIP   $ 167,282  
Construction Management Services   $ 365,564  
Progress Bar - Current Phase of Construction
Progress Bar - Completed
Project Team
Logo - Chumney & Assoc. Architect: Chumney & Associates
Logo - Spaw Glass Contractors General Contractor (GC):Spaw Glass General Contractors
Abie Flores Project Coordinator, NEISD, Construction Management
Shane Crawford MEP Inspector, NEISD, Construction Management
Progress Photos Bulverde Creek ES - Progress Photos
Bulverde Creek ES Campus: 3839 Canyon Parkway , San Antonio, TX 78259
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues.